Interactive Activity Network

Precedence Table

IDDurationPredecessors (comma-separated)

Tip: IDs must be unique. Leave predecessors blank for start activities.

Calculated Schedule

ActDurESEFLSLFFloatCritical
A303030CRITICAL
B235683
C437370CRITICAL
D2798101
E37107100CRITICAL
F2101210120CRITICAL
Critical Path: A → C → E → F

Network

A (3) ES 0 | EF 3LS 0 | LF 3 B (2) ES 3 | EF 5LS 6 | LF 8 C (4) ES 3 | EF 7LS 3 | LF 7 D (2) ES 7 | EF 9LS 8 | LF 10 E (3) ES 7 | EF 10LS 7 | LF 10 F (2) ES 10 | EF 12LS 10 | LF 12